Atlantic Delivers on DHL Project
A Corrugated Steel Stormwater Tank, installed nearly two years ago needed to be extended to accommodate more run off generated by new development. The existing tank was a 2.4mtr dia x three rows, with interconnecting manifolds at each end. The plan was to extend the middle sections by exhuming the manifold end, re-excavating, placing the extension legs and re-placing the original manifold.
Although the existing tank was not of Atlantic manufacture, our site team carried out a site survey to establish the exact dims for the diameter and length of each leg, to ensure a perfect match from the “Old” to the “New”.
Stainforth Construction Ltd were so pleased with Atlantic’s performance on previous recent projects; that they wanted us to deliver on this fast track project
< back to case studies